The recent completion of a major water pipeline project linking KALBA with Wadi Al Helu in Sharjah marks a significant advancement in water supply and infrastructure maintenance. The Sharjah Electricity, Water and Gas Authority has successfully executed this initiative, which includes the construction of a pumping station, along with six pumps and multiple tanks, at a cost of 43.77 million dirhams. This endeavor is part of ongoing efforts to enhance the quality and efficiency of drinking water distribution across the emirate.
Details of the Major Water Pipeline Project in Wadi Al Helu
The major water pipeline project in Wadi Al Helu represents a tangible extension of the comprehensive development plans implemented by the Sharjah Electricity, Water and Gas Authority under the directives of His Highness Sheikh Dr. Sultan bin Muhammad Al Qasimi, Member of the Supreme Council and Ruler of Sharjah. It has been closely monitored by His Highness Sheikh Sultan bin Muhammad bin Sultan Al Qasimi, Crown Prince and Deputy Ruler of Sharjah, along with the Executive Council. The initiative aims to provide advanced water services that meet the needs of residents while keeping pace with the latest technologies.
The main activities within this project include extending a 400mm pipeline from the Authority to supply an underground concrete tank and establishing a pumping station capable of handling 700,000 gallons daily (approximately 60 liters per second). Additionally, the project incorporates four main pumps (three operational and one backup) and two subordinate pumps to maintain continuous water pressure in the lines. The steel pipe network, ranging from 100mm to 300mm in diameter, stretches 20 kilometers from KALBA to Wadi Al Helu. Future expansion includes a connection to Jebel Deem and a fiber optic cable spanning 23.4 kilometers, as well as two elevated steel tanks in the area.
Technical Challenges Encountered in Completing the Pipeline Project
The Sharjah Electricity, Water and Gas Authority achieved a 100% completion rate for the water pipeline project in Wadi Al Helu, which involved stages of testing and operating the pumping station, flushing and disinfecting water lines and tanks, and implementing protective measures for steel pipes and tanks. This project overcame several mechanical and geographical challenges, including work in rugged mountainous areas and close proximity to active public roads, as well as adverse weather conditions and rainfall. The use of the latest materials and technologies helped ensure the long operational lifespan of the pipeline and achieve global standards in quality and safety, enhancing the efficiency of distribution networks and ensuring a stable water supply for Wadi Al Helu and surrounding areas.
Significance of the Major Water Pipeline Project for Sustainable Development
The implementation of the major water pipeline in Wadi Al Helu contributes to increased water stability and enhances the capacity of the Wadi Al Helu region. This aligns with evolving urban and population development plans, delivering high-quality water pressure to consumers and supporting the economic, tourism, and cultural projects taking place in the area. The Authority reaffirms its ongoing commitment to meeting energy and water needs according to the best standards and is actively studying and executing development projects that align with the aspirations of local residents, thereby enhancing water security in Sharjah for the future.
| Item | Specifications |
|---|---|
| Project Cost | 43.77 million dirhams |
| Length of Transmission Line | 20 km (Steel pipes 100–300 mm) |
| Pumping Station | 700,000 gallons daily (60 liters/second) |
| Number of Pumps | 6 pumps (4 main, 2 subordinate) |
| Tanks | Underground concrete tank and two elevated steel tanks |
| Fiber Optic Cable | 23.4 km for future connections |
The major water pipeline project in Wadi Al Helu underscores the commitment to advancing sustainable water solutions that meet the evolving needs of the Sharjah region.