Dubai has awarded new contracts worth about AED56.5 billion for the expansion of Al Maktoum International Airport, moving the strategic project into a phase of large-scale construction. The works cover passenger facilities, aircraft concourses, transport and energy systems, and the infrastructure and services needed to support the airport’s future operations.
Major investment in Dubai’s aviation future
Sheikh Hamdan bin Mohammed bin Rashid Al Maktoum said: “The vision of Sheikh Mohammed bin Rashid Al Maktoum, Vice President and Prime Minister of the UAE and Ruler of Dubai, has established Dubai among the world’s leading aviation hubs. Under his direction, we are today announcing new contracts worth nearly AED56.5 billion for Al Maktoum International Airport. This will enable us to deliver Dubai’s new global airport and reinforce the emirate’s leadership in aviation for decades to come.”
He described Al Maktoum International Airport as a project for future generations and a strategic investment in Dubai’s future, economy and global standing. Progress at the site, he said, reflects Dubai’s approach to turning major ambitions into achievements. The project will strengthen the emirate’s capacity to accommodate expected growth in passenger and cargo traffic, while supporting the Dubai Economic Agenda D33 goal of doubling the size of the economy and expanding its links with global markets.
Sheikh Ahmed bin Saeed Al Maktoum, chairman of Dubai Aviation City Corporation and of Dubai Aviation Engineering Projects, said the airport development had entered a phase of large-scale construction. He described the new awards as an unprecedented milestone for infrastructure projects in Dubai and the UAE, reflecting both the exceptional scale of the airport and the pace of its delivery.
“These awards mark a historic milestone in the project,” he said. “The unprecedented volume of contracts reflects the scale of the development and the investment Dubai is making today in infrastructure that will serve future generations and support the growth of aviation and the economy for decades to come.”
Sheikh Ahmed said the first phase was progressing according to the approved programme, with contracts and construction stages arranged to allow work to proceed simultaneously across several sites while maintaining the highest standards of quality and safety. Once operational, he said, the airport would give Dubai the capacity needed to accommodate the growth of national carriers and the expected increase in passenger and cargo traffic over the coming decades.
Construction gathers pace across the site
Dubai Aviation Engineering Projects had previously awarded contracts and packages worth about AED23.815 billion. These covered enabling works and substructures at several project locations, as well as contracts for the automated passenger transport system and the baggage-handling system. Including the latest awards of about AED56.5 billion, the total value of contracts and packages awarded for Al Maktoum International Airport now stands at around AED80 billion.
Construction is under way across the passenger terminal areas, aircraft concourses, tunnels, transport facilities and services. Enabling works are nearing completion around concourses 2 and 3 and in the airport’s central area. These works include baggage-handling tunnels, routes for ground support equipment and the main baggage-handling system interconnection network.
Enabling work is also continuing in the central passenger-terminal area, which includes the western passenger terminal, concourse 1 and the ground transport centre, as well as at concourse 4. More than 24.23 million cubic metres of excavation have been completed, along with over five million cubic metres of fill, while 7,635 piles have been installed.
Across the substructure packages for concourses 2 and 3, baggage-handling tunnels and ground support equipment routes, more than 875,603 cubic metres of concrete have been poured and over 226,000 tonnes of reinforcing steel installed. The work is paving the way for construction of the superstructures in these areas.
About 14,000 people are working on these packages, and the total recorded work has exceeded 21 million hours.
What the new contracts cover
The new awards include substructures and associated infrastructure for the western passenger terminal and concourses 1 and 4. They also cover the superstructures, architectural works and building systems for concourses 2 and 3, as well as major electrical infrastructure, including main substations and their associated networks.
The contracts allow construction to advance in parallel across several key facilities in the first phase. The work supports the integrated development of passenger buildings, underground transport links, utility networks and the operational infrastructure required by the airport.
At the western passenger terminal and concourse 1, the contracts cover extensive substructure and infrastructure works, including the underground facilities and structural foundations required for later stages of development. The scope includes basements, tunnels, access ramps, short-term parking and the ground transport centre, as well as connections to the metro network, landside bridges and related infrastructure.
The works also include underground corridors for aircraft ground support equipment (GSE), the main baggage-handling system (BHS) network and supporting utility networks. These include electricity, water supply, telecommunications, sewage and stormwater drainage.
Together, the works will provide the foundations and core infrastructure needed for the future superstructures of the western passenger terminal and concourse 1, while connecting them with the airport’s transport, baggage-handling and utility systems.
The awards also cover the superstructures for concourses 2 and 3, building on substantial progress already made on their substructures. The work includes the main structural frames, roof space frames and supporting vertical elements, circular atriums, steel bridges and structures supporting passenger boarding bridges.
It also covers external façades, roofing systems, finishes and architectural fit-out, mechanical, electrical and plumbing (MEP) works, and specialist airport systems in both concourses.
The substructure package for concourse 4 includes basements, tunnels, ramps and networks for electricity, water and telecommunications, as well as sewage and stormwater drainage systems, ground support equipment routes and the main baggage-handling network.
These works will provide the foundations and essential infrastructure for the later stages of concourse 4 and ensure its integration with the airport’s other facilities.
Power infrastructure and project delivery
The energy works include the construction of two main 132/11-kilovolt electricity substations, the installation of connecting cables, and testing, commissioning and handover. The package is intended to ensure reliable power for the airport’s facilities and operational systems.
The electrical works form part of the wider programme to develop the airport’s utilities and services, with infrastructure delivery coordinated with the construction, fit-out and operational preparation of its main facilities.
Dubai Aviation Engineering Projects leads and manages the airport development programme from planning and design through procurement and construction to operational readiness. It oversees the sequencing of contract packages, technical interfaces, quality, safety, costs and schedules, working with government entities and partners to deliver the facilities in line with the approved vision and future operational requirements.